By installing two giant transformer devices;

Lamerd Investors’ Power Supply Puzzle Complete

The ‎‎power supply puzzle‎‎ of the investors of Lamerd Special Economic Zone was completed with the arrival and installation of two super-distribution transformers to Lamerd Special Economic Zone. ‎

‎According to the Public Relations of the Iranian Mines and Mineral Industries Development and Renovation Organization (IMIDRO), quoting the public relations of Lamerd Special Energy Industries Zone, in coordination with Fars Regional ‎‎Electric Company‎‎, two transformers with a power of 50,000 kVA were added to the ‎‎power‎‎ supply capacity of this special area.‎

‎With planning and railing, and in order to increase the capacity of sustainable ‎‎electricity‎‎ supply for aluminum downstream industries and other new industries, the project of construction ‎‎of a‎‎ 132/20 kV substation was defined which is now approaching 90 percent progress with the arrival and installation of these two transformers.‎