According to the Public Relations of Ghaenat Steel Complex, the operation of launching and functional testing (PGT) of the oxygen plant of Ghaenat ️Steel Complex was successfully completed on May 11, 2025.
It is worth noting that ️this is the first oxygen plant in the country that has been set up without the presence of foreign experts and just relying on the technical capabilities of domestic forces.
️The production capacity of this unit is as follows:
Gaseous oxygen: 5500 normal m3/h, with a purity of 99.6%
Liquid oxygen: 72 kg/h, with a purity of 99.6%
gaseous nitrogen: 2000 normal m3/h, with a purity of 99.6%
liquid nitrogen: 62 kg/h, with a purity of 99.6%
Liquid argon: 285 kg/h, with a purity of 99.999%
Hadi Abdi,Managing Director of Ghaenat Steel Complex, congratulated all who were involved in this project and also appreciated the honest and professional efforts of all colleagues in achieving this success.